Henry Gantt : biography
Gantt (1903) describes two types of balances:Gantt, Henry L., A graphical daily balance in manufacture, Transactions of the American Society of Mechanical Engineers, Volume XXIV, pages 1322–1336, 1903.
- the "man’s record", which shows what each worker should do and did do, and
- the "daily balance of work", which shows the amount of work to be done and the amount that is done.
Gantt gives an example with orders that will require many days to complete. The daily balance has rows for each day and columns for each part or each operation. At the top of each column is the amount needed. The amount entered in the appropriate cell is the number of parts done each day and the cumulative total for that part. Heavy horizontal lines indicate the starting date and the date that the order should be done. According to Gantt, the graphical daily balance is "a method of scheduling and recording work". In this 1903 article, Gantt also describes the use of:
- "production cards" for assigning work to each operator and recording how much was done each day.
In his 1916 book "Work, Wages, and Profits" Gantt, Henry L., Work, Wages, and Profits, second edition, Engineering Magazine Co., New York, 1916. Reprinted by Hive Publishing Company, Easton, Maryland, 1973. Gantt explicitly discusses scheduling, especially in the job shop environment. He proposes giving to the foreman each day an "order of work" that is an ordered list of jobs to be done that day. Moreover, he discusses the need to coordinate activities to avoid "interferences". However, he also warns that the most elegant schedules created by planning offices are useless if they are ignored, a situation that he observed.
In his 1919 book "Organizing for Work" Gantt, Henry L., Organizing for Work, Harcourt, Brace, and Howe, New York, 1919. Reprinted by Hive Publishing Company, Easton, Maryland, 1973. Gantt gives two principles for his charts:
- one, measure activities by the amount of time needed to complete them;
- two, the space on the chart can be used to represent the amount of the activity that should have been done in that time.
Gantt shows a progress chart that indicates for each month of the year, using a thin horizontal line, the number of items produced during that month. In addition, a thick horizontal line indicates the number of items produced during the year. Each row in the chart corresponds to an order for parts from a specific contractor, and each row indicates the starting month and ending month of the deliveries. It is the closest thing to the Gantt charts typically used today in scheduling systems, though it is at a higher level than machine scheduling.
Gantt’s machine record chart and man record chart are quite similar, though they show both the actual working time for each day and the cumulative working time for a week. Each row of the chart corresponds to an individual machine or operator. These charts do not indicate which tasks were to be done, however.
A novel method of displaying interdependencies of processes to increase visibility of production schedules was invented in 1896 by Karol Adamiecki, which was similar to the one defined by Gantt in 1903. However, Adamiecki did not publish his works in a language popular in the West; hence Gantt was able to popularize a similar method, which he developed around the years 1910–1915, and the solution became attributed to Gantt. With minor modifications, what originated as the Adamiecki’s chart is now more commonly referred to as the Gantt Chart.Gerard Blokdijk, Project Management 100 Success Secrets, Lulu.com, 2007, ISBN 0-9804599-0-7, Peter W. G. Morris, The Management of Projects, Thomas Telford, 1994, ISBN 0-7277-2593-9,